Wednesday, November 18, 2009

AUDIT OBSERVATION MEMORANDUM NO. 9

AUDIT OBSERVATION MEMORANDUM NO. 9. LGU of Bulan, Sorsogon failed to post a procurement opportunity with the PhilGEPS in violation of Section 8-IRR-A of Republic Act No. 9184.


DISCUSSION:

The Philippine Government Electronic Procurement System (PhilGEPS) has adopted a two-pronged approach to achieve the following, to wit:

a. Institutionalization of the PhilGEPS, which will be used for the procurement of common-use items and as repository of all Government procurement information, and

b. Use or engagement of electronic procurement service providers by the Individual Procurement Entities for procurement of non-common use items.


The Procurement System – Department of Budget and Management (PS-DBM) manages the PhilGEPS under the supervision of the Government Procurement Policy Board (GPPB). The PhilGEPS serves as the single portal and primary source of information on all government procurement.


All Procuring Entities shall utilize the PhilGEPS, through its Electronic Catalogue facility, for the procurement of common-use supplies. Moreover, all Invitation to Apply for Eligibility and to Bid (IAEB), notices of award, and all other procurement-related notices shall be posted in the PhilGEPS, regardless of the method of procurement used by the Procuring Entity.


The GPPB shall issue the necessary procedural guidelines covering procurement through the PhilGEPS.


The PhilGEPS shall have a centralized electronic bulletin board. Procuring Entities are required to post the following in the PhilGEPS Electronic Bulletin Board:

i. IAEB for competitive bidding and notices of other procurement opportunities using the alternative methods of procurement;

ii. Supplemental/Bid bulletins

iii. Contract awards, the corresponding Notices of Award, including the reasons for award of contract;

iv. Results of bidding and related information; and

v. Other notices, announcements, information for interested parties.

Failure to post a procurement opportunity will render the resulting contract null and void. Failure to post a Notice of Award shall render the erring government official/s administratively liable in accordance with R.A. 6713 and other pertinent laws, rules and regulations, and appropriate sanctions shall be imposed.


Posting of notices and other transactions shall be done through duly authorized personnel of the Procuring Entity. In accordance with Section 8.2.3 of the Implementing Rules and Regulations for Domestic Project (IRR-A), the Procuring Entity shall be required to designate its personnel who will be authorized to transact with the PhilGEPS. The internal procedures of PhilGEPS require that a Procuring Entity shall have at least one (1) but not more than two (2) such authorized personnel. For purposes of consistency with the prescribed procurement procedures, the Procuring Entity shall designate such personnel who is a member of the BAC Secretariat or assigned to the Procurement Unit/Office.


Posting the IAEB shall follow the guidelines in Section 21 of the IRR-A, Section 2, Part 1, Vol. 2, Section 3, Part 1, Vol. 3, and Section 3, Part 1, Vol. 4 of said Manual.


The PhilGEPS shall have a centralized electronic database of all manufacturers, suppliers, distributors, contractors and consultants registered under the system. Registration shall entail the submission of the requirements specified by the PS-DBM. Details of the requirements may be obtained from the PS-DBM website or PhilGEPS website.


Registration with the PhilGEPS is not tantamount to a finding of eligibility, nor is it a guaranty that a manufacturer, supplier, distributor, contractor or consultant may participate in a public bidding without first being determined to be eligible for that particular public bidding.


Procuring entities without internet access may avail of the PhilGEPS Public Access Terminals which shall be installed at DBM-designated locations in the provinces and in Metro Manila.

The PhilGEPS also feature the following:

Ø A Virtual Store that will enable the ordering of common-use and non-common use items online called a virtual store. This virtual store shall be open only to registered Procuring Entities and may not be accessed by suppliers.

Ø An Electronic Payment function that will allow the system to manage the generation of purchase orders and the payment of bids processed through the system. The focus of this feature is to facilitate the electronic transfer of funds from PS-DBM to and from Procuring Entities and suppliers, and from Procuring Entities to suppliers for bids managed directly by the Procuring Entity. This System will:

· Generate purchase orders from a bid notice, award notice or contract;

· Support approval process for purchase orders before any payment or fund transfer is processed;

· Have a process to submit request for payment upon delivery of goods and/or services and the completion of the approval process; and

· Have the ability to interface with the designated bank of the Procuring Entity and suppliers to support the electronic transfer of funds.

Ø An Electronic Bid Submission that will support the implementation of e-Bid submission process, which includes creation of electronic bid forms, creation of bid box, delivery of bid submissions, notification to supplier of receipt of bids, bids receiving and electronic bid evaluation. This facility will cover all types of procurement for goods, infrastructure projects and consulting services.


Procuring Entities may hire service providers who will provide electronic procurement systems and/or services for the procurement of non-common use supplies, infrastructure projects and consulting services.


The Procuring Entity shall conduct a public bidding for this service.


Electronic procurement service providers must meet the following minimum requirements to qualify as a service provider to a Procuring Entity:

1. The system must comply with the provisions of R.A. 9184, its IRR-A, R.A. 8792 (Electronic Commerce Act);

2. The system must be linked to the PhilGEPS, particularly with regard to the posting of all bid opportunities and awards;

3. The system must allow parallel manual submission of bids to the Procuring Entity;

4. The system must ensure that the BAC shall have the complete control of the bidding process, and that the BAC’s sole authority to open bids is strictly observed;

5. The system must be virus-resilient and the infrastructure must provide sufficient security which is at least equivalent to that employed by the PhilGEPS, such as, but not limited to firewall and encryption devices;

6. Must provide for use of electronic signatures and other current electronic authentication devices;

7. The service provider must have sufficient redundant back-up facilities;

8. The system must have provisions for linkage to the Procuring Entity’s Financial Management Information System, and other internal information systems that may interact with the procurement process; and

9. Electronic payment facilities, if used, shall comply with all laws, rules and regulations issued by the Government.


The GPPB shall determine and certify compliance with the above requirements. However, it may delegate this task to technically capable agencies/offices of the Government. For this purpose, it shall issue the necessary Guidelines.


Our audit disclosed that LGU Bulan, Sorsogon failed to register with the PhilGEPS and as a consequence the following information were not posted in the PhilGEPS Electronic Bulletin Board as Procuring Entities required to post the abovementioned information to the PhilGEPS Electronic Bulletin Board.


Moreover, analysis of the comparative results of bid prices under BAC Resolution Nos. 12 and 13 for Bus Terminal and Slaughterhouse, respectively, revealed that comparative analysis results were not also posted in the G-EPS Bulletin Board for their information records and reference purposes, as shown hereunder to wit:

CONSTRUCTION OF BULAN BUS TERMINAL

Name of Bidder


Bid Price


Difference


Ave. Difference


Remarks







P11,100.00



S.R. Baldon Construction & Supply


P32,984,700.00






winning/lowest bidder

BSB Construction & Supply


P32,993,200.00


P8,500.00




2nd lowest bidder

CTC Builders & Supply


P32,998,400.00


P13,700.00




3rd lowest bidder










CONSTRUCTION OF SLAUGHTERHOUSE

Name of Bidder


Bid Price


Difference


Ave. Difference


Remarks







P3,500.00



Steven Construction & Supply


P4,991,800.00






winning/lowest bidder

Muntopar Builders


P4,994,400.00


P2,600.00




2nd lowest bidder

Necen Builders


P4,996,200.00


P4,400.00




3rd lowest bidder

The above cited schedule of Contractor’s Bids and analysis of the result of the Lowest Calculated Responsive Bid (LCRB) as recommended by BAC Resolution Nos. 12 and 13 revealed that, as if there was no competitive public bidding that took place or had transpired which registered the lowest average difference of P11,100.00 over the other two bidders for the Bus Terminal project while, it likewise registered the least average difference of P3,500.00 over the other two bidders for the Slaughterhouse project.


An in-depth analysis of post-evaluation activity of the bidding process was not seriously undertaken by BAC which showed that the difference of two projects bidded were minimal. This cast doubt on the results of bidding procedures made by the BAC as shown on the table abovementioned.


COA’S RECOMMENDATION:

Require the duly authorized personnel, designated/assigned to the procurement office to explain in writing why they failed to register the Procuring Entity/LGU with the PhilGEPS that likewise resulted in the failure to post the same in the PhilGEPS centralized electronic bulletin board pursuant to Section 8-IRR-A of R.A. No. 9184.


LGU’S COMMENT:

The procurement opportunity for the implementation of the twin projects was posted in a newspaper of national circulation. Due to the recurring technical problems plaguing the fledgling internet industry in the area at the time, posting with PhilGEPS was inadvertently omitted by the BAC. The recent observation of the commission is a wake-up call that was immediately addressed by the LCE. The BAC Chairman was directed to coordinate with concerned agencies for the immediate and proper training of BAC members and support personnel. The LCE also tasked the body to immediately enrol the LGU with PhilGEPS.


COA’S REJOINDER:

The diligence of a good father of a family was not exercised by the procuring entity pursuant to Section 8-IRR-A of R.A. No. 9184. Procuring entities without internet access may avail of the PhilGEPS Public Access Terminals which shall be installed at DBM-designated locations in the provinces and in Metro Manila.


Failure to post a procurement opportunity will render the resulting contract null and void. Likewise, failure to post a Notice of Award shall render the erring government officials administratively liable in accordance with R.A. 6713 and other pertinent laws, rules and regulations, and appropriate sanctions shall be imposed.

1 comment:

  1. We have been using Mr Benjamin financial team to help secure our first acreage block. We are happy with the professionalism In Financial Services Mr Benjamin and his loan company brings to the table with the loan rate of 2% interest rate that we use to get our loan from Mr Benjamin we are also doing a separate construction loan with them. Everything has been a breeze with the team behind Mr Benjamin which is  100%  of the way, and no question is too silly to ask. Would recommend this Loan officer to anyone looking for a loan at the low rate of 2% RIO!! Email Mr Benjamin and his team today for any kind of loan 247officedept@gmail.com      Whats-App Number  +1-989-394-3740

    ReplyDelete