AUDIT OBSERVATION MEMORANDUM NO. 8

AUDIT OBSERVATION MEMORANDUM NO. 8. Bond flotation semi-annual interest from December 5, 2006 to December 5, 2007 in the amount of P3.436 million could have been saved had the municipal government of Bulan, Sorsogon set-aside bond flotation as the mode of financing the project, although as a consequence a loan agreement made, executed and notarized on September 3, 2007 by and between LGU Bulan, Sorsogon and LBP Legaspi Branch, to refinance the same project.


DISCUSSION:

The Sangguniang Bayan of LGU Bulan, Sorsogon confirmed and ratified, ordinance No. 004 series of 2003, authorizing the Bond Flotation of the Municipality of Bulan, Sorsogon in the amount not exceeding Fifty Million (P50,000,000.00) to fund the construction and development of Bulan Bus Terminal and Municipal Slaughterhouse, represented by Mayor Guillermo O. De Castro and DPEM Inc. represented by its President Junio M. Ragrario.

1. The Municipality is hereby authorized to issue and float “Bulan Bonds” under the terms and conditions set forth and agreed upon with any person, corporation or entity for the purpose of constructing the projects abovementioned and the power and authority in negotiating the terms and conditions for the said “Bulan Bonds” and signing and executing and delivering such agreements, contracts, deeds, papers and documents necessary for the full and total implementation of the authority granted.

2. The features and terms and conditions of the bond flotation is provided in Section 2 of said ordinance abovementioned to wit:

BULAN BONDS

Bond Name

Bulan Bonds

Issuer

Municipality of Bulan

Amount

P50 million, in staged tranches as allowed by the financial capacity of the Municipality

Issue

Registered local government bonds of the Municipality of Bulan (“Bulan Bonds)

Purpose

Construction of the twin projects, etc.

Offering Price

100% of face value

Term

Mixed term up to ten (10) years from issue date

Denomination

P1,000; P10,000; P100,000; and P1,000,000

Medium of sale

1) Public offering; 2) Private placement; and 3) Direct payment to suppliers, contractors, or project developers/proponents

Manner of Payment


Interest

Semi-annual fixed or floating rate

Principal

Balloon principal repayment at the end of the seventh or tenth year from issue date and/or principal payments amortized equally starting the third year or later following issues of different terms

Interest rate

Interest shall be floating based on the weighted average of the 182-day Treasury Bill (T-Bill) rate

Collateral/Guarantee/Security

Proceeds from revenue of project improvements and facilities funded by proceeds of the bond, and assignment of Internal Revenue Allotment

Trustee/Fiscal Agent

Any government bank to be designated by the Municipal Mayor, to act as a fiscal agent, handle the sinking fund, act as fund manager, transfer agent and paying agent

Trustee fee

Up to ½ of 1% per annum

Underwriting

Any government or private financial institution licensed to undertake underwriting of securities as allowed under Philippine laws

Guarantor

LGU Guarantee Corporation (LGUGC) or any other appropriate institution

Guarantee fee

One-time fee chargeable to developers, proponents, contractors, or investors of the project

Moreover, Section 3 to 9 of the subject ordinance provides among others several conditions for the LGU, to wit.

3. To appropriate the entire proceeds of the bonds, upon its successful issue exclusively to finance the construction of the twin projects and to pay for the financial advisory fee and trustee fee and other financial obligation relative thereto;

4. To appropriate in the municipal annual budget such amount necessary to fund the sinking fund that will be created through the appointed trustee bank;

5. To designate a government depository bank to act as trustee or fiscal agent for the Bulan Bonds, to sign and execute any trust indenture agreement and deed of assignment, relative to the designation of said bank and flotation of the bond;

6. The Municipal Mayor shall appoint, any government or private institution duly licensed as underwriter to be the underwriter of the Bulan Municipal Bonds “Bulan Bonds” and to negotiate, sign and execute an underwriting with the said underwriter in such form and substance to be ratified by the Municipal Council;

7. The Municipal Mayor may designate the LGU Guarantee Corporation, a Corporation organized by the Bankers Association of the Philippines, to specifically extend guarantee on the Bulan Municipal Bonds and for this purpose the Municipal Mayor is likewise authorized to negotiate, sign and execute any contract or agreement with the LGU Guarantee Corporation pertinent to bond flotation in such form and substance to be ratified by the Municipal Council. The Municipal Mayor, however, may undertake alternative agreements should such be necessary due to cost considerations.

8. The Municipal Mayor is authorized to conduct public bidding on the awarding of the projects to be funded through bond flotation either on a design and construct basis or on a construct basis with the developer/contractors to be paid either in the form of Bulan Bonds and/or cash proceeds from bond’s sale. The procedure of such bidding shall be done in accordance with applicable provisions of PD 1594, usual auditing and accounting rules and regulations, relevant Municipal Ordinances and such procedures which the Municipal Mayor may deem necessary in the implementation of the municipal’s bond flotation project or projects. The Municipal Treasurer shall issue the corresponding Certificate of Funds Availability out of the proceeds of the Bond Flotation.

9. The Memorandum of Agreement entered into by and between the Municipal Government of Bulan, represented by its Mayor, the Honorable Guillermo O. De Castro, as authorized by the Sangguniang Bayan and DPEM Inc. represented by its President, Junio M. Ragrario, for purposes of the bond flotation is hereby confirmed and ratified.


Our audit disclosed that LGU Bulan, Sorsogon have incurred unnecessary expenses of P3.436 million for two semi-annual interest from December 5, 2006 to December 5, 2007, excluding financial advisory fee, trustee fee and other financial obligations relative thereto. Although as a consequence, a loan agreement was made and executed on September 3, 2007 by and between the LGU Bulan and LBP Legaspi Branch just to refinance the project with the corresponding promissory with assignment of Internal Revenue Allotment (IRA) and revenues from the project as collateral.


COA’S RECOMMENDATION:

Require the Sangguniang Bayan of LGU Bulan, Sorsogon to justify in writing why they resorted the bond flotation instead of direct loan with the same bank which could have avoided such incurrence of unnecessary expenses amounted to P3.436 million and proper identification of other expenses incurred in addition thereto in detail.


LGU’S COMMENT:

The administration of Mayor Guillermo O. De Castro can be credited for transforming Bulan from a backwater municipality, dark and littered with dirt and refuse. After illuminating and cleaning the town, the then-LCE opened roads and access to even the remotest village. Prior to 2003, it became evident that the price of development is caching up with the municipality. By then, the premier commercial and educational center in the part of the province, congestion, overcrowding and related problems were weighing heavily on the populace. Concerned government agencies suggested decongestion. Transportation terminals, slaughterhouses, cemeteries and the like were all situated in and around the center of the poblacion. Tackling the problems heads-on, the administration tried to secure financing from bank and government agencies. With prospective fund sources unable to accommodate the LGU, the municipality opted to raise the money thru the only available option: bond flotation. Ironically, offers of straight loan came in droves after the flotation, entice, no doubt, by the LGU’s increased IRA-share.


The then-LCE and the then-Sangguniang Bayan were not remiss in the performance of their duties. Doing their best, they were hampered by the circumstances such as the dearth of loan-providers. Given the situation obtaining today, those community leaders would have opted for a straight loan.


The 8.9% Bulan Bonds cost the LGU some P3.436 million in interest payment for the period covering December 5, 2006 to December 5, 2007. If the municipality were granted a simple straight loan in the same period at the prevailing rate of 8.53% the interest payment for the first year would have been P3.412 million or a difference of P24,000. Indeed, the entity could have saved P24,000 on interest and on the transaction cost; but only if the situation in 2006 were similar to that in 2007. And they were not.


In 2003, the LGU was facing a looming problem of congestion brought about by haphazard town-planning. The municipality had 2 alternatives: address the problem now or wait for “better” times. With spiralling prices, “better” times would mean bigger implementing cost. The LGU, like a good father to its constituents, addressed the problem by utilizing the best option available to it at the time to deliver the service demanded of it by its people.


The experience, though, provided the LGU with a better insight of the financing community. In times of similar needs, the LGU can tap on its experience and be guided by other government entities such as the Commission on Audit.

Sunday, November 1, 2009

AUDIT OBSERVATION MEMORANDUM NO. 7

AUDIT OBSERVATION MEMORANDUM NO. 7. Premature conversion activities were undertaken by LGU Bulan, Sorsogon of a Riceland donated by Mrs. Anecita O. De Castro to be developed into a Bus Terminal from October 4, 2006 prior to awarding of the contract to S.R. Baldon Construction & Supply on December 11, 2006.


DISCUSSION:

Premature conversion activities were undertaken by LGU Bulan, Sorsogon on the Riceland donated by Mrs. Anecita O. De Castro as the site of Bulan Integrated Bus Terminal. As of October 4, 2006, almost half hectare (1/2 ha.) has been filled up with truck loads of soil fillers. Likewise hollow blocks are already present within the area as a result of the ocular inspection made by Mr. Gil G. Garido, Municipal Agrarian Reform Officer of Bulan, Sorsogon. This information was transmitted to Mr. Roseller R. Olayres, OIC-PARO II, DAR Provincial Office, Balogo, Sorsogon City, and Atty. Juan F. Zulueta, Chairman, Provincial Task Force on Illegal Conversion, copy furnished, the Regional Director and Regional Task Force on Illegal Conversion pursuant to AO No. 1 Series of 2002, and AO No. 4 Series of 2003.


With the foregoing facts and information, the Municipal Engineer and the Zoning Officer III/Project In-Charge should determine the quantity of truck loads of soil fillers in terms of cubic meters and hollow blocks and the corresponding size delivered to the project site and the corresponding computation of its equivalent money value.


COA’S RECOMMENDATION:

Require the Municipal Engineer and Zoning Officer III/Project In-Charge to quantify the alleged/actual deliveries of soil fillers in terms of cubic meters and the number of pieces of hollow blocks and the corresponding size delivered to the project site and the corresponding computation of its equivalent value in terms of pesos is likewise reiterated.


LGU’S COMMENT:

The LGU has no record of premature conversion activities of the lot donated by Ms. Anecita O. De Castro. Pictures of proposed projects sites included in the application for Environmental Compliance Certificate would show that the particular lot was vacant and free of construction materials prior to actual projects implementation. There is a strong possibility that the area, being vacant, was temporarily utilized by businesses in the vicinity. It was recalled that there was, at a time, an on-going construction on the lots adjacent to the terminal.

AUDIT OBSERVATION MEMORANDUM NO. 6

AUDIT OBSERVATION MEMORANDUM NO. 6. Construction of Bulan Integrated Bus Terminal and Slaughterhouse as published on the “Philippine Star” dated September 15 and 22, 2006 issues states that funding source was through Municipal Bond Issue in the amount of P33 million and P5 million respectively, while on the contrary said twin projects was funded through a loan from LBP in the amount of P38,486,744.52 dated September 10, 2007 to refinance the same.


DISCUSSION:

The Municipal Government of Bulan, Sorsogon thru the Bids and Awards Committee awarded the construction of Bulan Bus Terminal to S.R. Baldon Construction Supply, on December 11, 2006 in the amount of P32,984,700.00, while the construction of slaughterhouse was awarded to Steven Construction & Supply dated December 29, 2006 in the amount of P4,991,800.00 in the total amount of P37,976,500.00 as against the aggregate amount of loan granted by the bank of P38,426,744.52 which revealed a difference of P450,244.52.


The contract agreement for the construction of Bus Terminal was notarized on December 31, 2006, and for the construction of Slaughterhouse was likewise notarized on December 29, 2006. As a consequence, Resolution No. 033, series of 2007 was passed by the Sangguniang Bayan of Bulan, Sorsogon, authorizing the Hon. Mayor Helen C. De Castro for and in behalf of the LGU Bulan, Sorsogon, to apply, negotiate and enter into a contract og loan with LBP, Irosin Branch, Province of Sorsogon. A loan agreement made and executed at Legaspi City on September 3, 2007 by and between the LBP Legaspi Branch and the Municipal Government of Bulan, Sorsogon for the purpose of refinancing the construction of Bulan Bus Terminal and Municipal Slaughterhouse originally funded by LBP-TBG (Trust Banking Group) via issuance of Bulan Bonds while on the other hand, again a Promissory Note with Assignment of Internal Revenue Allotment (IRA) and Revenues from the project was entered into by and between the Municipal Government of Bulan, Sorsogon and the Land Bank of the Philippines (LBP) Legaspi Branch represented by Mayor Helen C. De Castro and Dept. Mgr. Hil Benedict G. Manzanades, respectively, effective September 10, 2007.


Purchase Order (PO) No. 029 and Unnumbered PO both dated October 29, 2006, were certified by the Municipal Accountant that there is funds available and approved by the requisitioning officer, the Municipal Mayor for the construction of Bulan Integrated Bus Terminal at Brgy. Fabrica, Bulan, Sorsogon and construction of slaughterhouse at Zone 7, Bulan, Sorsogon, respectively.


Our audit disclosed that analysis and verification of pertinent document revealed that the source of fund as published as of the awarding of contract on December 11, 2006 was via issuance of Bulan Bonds, while on the contrary the source of funding was through a succeeding loan agreement at LBP approved on September 10, 2007. The project was on-going since December 8, 2006 after a lapsed of more than eight (8) months after said loan was approved and released by the bank.


COA’S RECOMMENDATION:

Require the Municipal Accountant to explain in writing, why funds availability for the twin projects were certified both dated October 29, 2006, while the loan was approved on September 3, 2007 for the purpose of refinancing the construction of the twin projects abovementioned.


LGU’S COMMENT:

The certification on the availability of funds for the projects was made on the basis of the “Underwriting Agreement” executed by and between the Local Government Unit of Bulan and the Land Bank of the Philippines on August 25, 2006. The agreement has “authorized the issuance of bonds in the aggregate amount of Forty Million Pesos to finance the improvement, construction and development of appropriate areas . . . as the sites of a new Municipal Bus Terminal and a new Municipal Slaughterhouse. That there indeed were funds available for the twin projects in 2006 is further evidenced by the charges against, and releases from, the same in the ensuing month of December, 2006, and during the first two (2) quarters of CY 2007, as follows:


DATE


PAYEE


AMOUNT

12/17/06


Junio Ragrario/DPEM Inc.


P1,200,000.00

1/5/07


CDF


1,284,000.00

1/8/07


S.R. Baldon Construction & Supply


4,947,705.00

1/8/07


Steven Construction & Supply


748,770.00

3/9/07


S.R. Baldon Construction & Supply


15,997,579.50

3/9/07


Steven Construction & Supply


1,747,130.00

4/27/07


S.R. Baldon Construction & Supply


4,165,968.00

4/27/07


Steven Construction & Supply


1,447,622.00

6/4/07


S.R. Baldon Construction & Supply


3,340,511.70

6/4/07


Steven Construction & Supply


1,048,278.00



TOTAL


P35,927,564.20


The Thirty Eight Million Four Hundred Twenty Six Thousand Seven Hundred Forty Four Pesos & Fifty Two Cents (P38,426,744.52) loan taken out of Land Bank of the Philippines, Legaspi City on September 10, 2007, was not intended to defray expenses connected with the construction of the twin projects. Rather, the entire proceeds were utilized to buy out and retire the “Bulan Bonds.”


COA’S REJOINDER:

The contract awarded in the amount of P32,984,700.00 registered a difference of P4,532,935.80 compared to the actual payments made by LGU Bulan, Sorsogon to S.R. Baldon Construction & Supply in the total amount of P28,451,764.20.


BAC Resolution No. 12, series of 2006 have determined S.R. Baldon Construction & Supply as the Lowest Calculated Responsive Bid (LCRB) in the amount of P32,984,700.00 for the construction of Bulan Integrated Bus Terminal.